Data Centre
United Kingdom,
Manchester
|
Control and power solutions |
Data Centre is supplied by three mains feeders which are supported by two standby diesel generators 2.2 MVA. System is a complete refit of controls and replacement generator sets for multiple internal (MINT) application with parallel to mains and inclusive of bus tie synchronising controls.
Floor standing control system furnished with:
- 2x InteliSys NT (load and VAR share)
- 1x InteliMains NT BTB for generator common bus
- 2x InteliMains NT with G59 protection
All of the above installed and commissioned at 415V.
ComAp Systems UK supplied a complete design and build package inclusive of:
- Generator controls
- Temporary interface to existing system for hire set period
- Mains control with repeater control system
- Remote monitoring package
- Controls and software to enable “Short Term Operating Reserve” (STOR)

United Kingdom,
Manchester